Example concrete flatwork plan, start to finish
Driveways, walks, aprons and steps with joints and finish. This is a real output from the concrete flatwork calculator — nothing blurred, nothing withheld. Change any dimension and yours regenerates instantly. Estimates only, never a quote.
- Type
- driveway
- Size
- 40×12 ft
- Thickness
- 5"
- Base
- 6"
- Concrete
- 8.05 cu yd
- Finish
- broom
Scaled diagram
Full shopping list
Ready-mix concrete (delivered) 8.86 cu yd × $172 | $1,524 |
Compacted gravel base (3/4"-minus) 9.78 cu yd × $42 | $411 |
Form lumber (2×6 × 12') 10 ea × $13 | $130 |
Form stakes 42 ea × $2 | $84 |
Expansion joint material 104 ft × $1 | $73 |
Finishing tools (float, edger, groover, broom) 1 kit × $78 | $78 |
Rebar #4 (18" grid) 766 ft × $1 | $421 |
Joint sealant (saw-cut joints) 76 ft × $1 | $84 |
Concrete sealer (broom finish) 2 gal × $34 | $68 |
| Incl. 10% waste ($261) | $2,872 |
Cut list
- Forms – long sides ×22×6 × 40'
- Forms – ends ×22×6 × 12'
- Control joints ×411' panels
- Rebar – long runs ×9#4 × 40'
- Rebar – short runs ×28#4 × 12'
Permit checkpoints
- Call 811 before you excavate
You're removing 11" of material across 480 sq ft. Free, required by law, and takes a few days — schedule it before the concrete order.
- Right-of-way / curb-cut permit
Any driveway or apron that touches the public sidewalk, curb or street needs a separate right-of-way permit from the city or state DOT, and the apron usually has to be built to their published detail — often 6" thick with specified rebar.
- Impervious-surface limits
Most municipalities cap the percentage of a lot that can be paved, and stormwater rules may require the runoff to stay on your property. Widening a driveway is the most commonly-cited unpermitted improvement.
- Building permit likely required
Flatwork over 200 sq ft (yours is 480 sq ft) usually needs a permit, especially where it changes drainage or supports vehicles.
- Pitch away from the house at 1/8" per foot
Over 12ft of width that's a 1.5" fall. Water toward a foundation is the most expensive mistake on this list.
- Cut control joints on time
Joints go in within 6-12 hours of the pour (or tooled during finishing), at a depth of one quarter of the slab thickness. Late joints crack where they want to, not where you planned.
Rules vary by city and county — always confirm with your local building department. Estimates only, not a permit determination.